Our Option A Requires about $550 million
Federal max = $600 million (approx.), so we can get 50% Federal funding.
That leaves $551/2 = $275 million to finance locally. - $137 from each of Oregon & Washington.
Oregon got $200 million for a LRT bridge, so they ought to be able to get $137 million for this.
Washington should also provide $137 million. (just 2 times what they have already spent on studying the mega-project!!)
# People losing jobs
due to tolls = ZERO
Federal (50%) = $275 million
Washington = $137 million